On Monday, November 16, the City of San Antonio closes the Voelcker Homestead Trailhead and its parking lot for a SAWS water line project. The closure is scheduled to run through summer 2027. The trailhead sits at 1021 Voelcker Lane. Friends of San Antonio Natural Areas counts more than 70 parking spaces in that lot, close to the midpoint of the Greenway stretch through Phil Hardberger Park.
About four weeks after that lot closes, Shavano Park expects to finish a 400-foot concrete trail from Cliffside Road down to the same Greenway. For Shavano Park, the timing works out well. Construction on a trail the city spent a year planning with residents is scheduled to wrap up just as the closest parking lot on that stretch closes for the season.
Two dates set this winter on the Salado
San Antonio's park closures page says the Salado Greenway segment through Phil Hardberger Park stays open during the SAWS work, with occasional temporary closures. You can still walk or ride the trail. The lot is what closes.
Here is how the two projects line up:
- November 6: Cliffside trail construction began with erosion control and tree protection.
- Week of November 9 through 13: Excavation and rock milling near the Cliffside bend.
- November 16: Voelcker Homestead Trailhead and parking lot close.
- Early December: Fence construction begins as the concrete work wraps up.
- Second week of December: Cliffside trail expected to be complete.
- Summer 2027: Voelcker Homestead Trailhead scheduled to reopen.
The city puts the full Cliffside build at about five weeks. If it stays on schedule, the Voelcker lot will have been closed for less than a month when work on the new path is complete.
What is being built at the Cliffside bend
The project page on the City of Shavano Park website describes a 6-foot-wide, 400-foot-long concrete nature trail. The concrete is colored light brown and textured for better grip. The earlier design notes say the brown color helps it blend into the forest floor. They also call for a brush-and-rock-salt finish for traction when the trail is wet.
The route drops 20 feet, from an elevation of 914 to 894. Most of it runs at a 5 to 6 percent slope, with one short section near Cliffside at 11 to 12 percent. It keeps a 30-foot buffer from nearby homes, and the engineering review found it meets ADA accessibility standards without switchbacks or added safety rails. The plan calls for about 300 feet of wrought-iron fence running from a corner lot on Cliffside to the point where the bluff becomes impassable. A gate will sit near an existing power source, so access controls could be added later.
The contractor is Abelar, Inc. The city says the same company built 12 miles of the Salado Creek Greenway.
How residents shaped the design
The trail's width and surface came from a public process, which is part of why the finished path will look the way it does. In October 2025, City Council asked the Planning & Zoning Commission to study a Cliffside entry point to the Greenway and set aside $25,000 for engineering. The commission formed a subcommittee and then picked eight residents from 19 applicants to serve on a Citizens Advisory Panel. The panel walked the route on February 25, 2026.
At the town hall on March 18, 2026, 62 people saw three options, and 42 of them answered the online survey.
| Option | Width | Surface | Notes from the city |
|---|---|---|---|
| A | 10 feet | Concrete | Same width as the Salado Creek Greenway, wide enough for cyclists and walkers to pass each other |
| B | 6 feet | Concrete | About the width of a typical roadside sidewalk; $170,000 with gate and fence |
| C | 6 feet | Loose gravel | Nature trail with higher maintenance |
Option B had the most support at 54.76 percent. On April 1, the commission recommended it to Council, and the recommendation was presented at the April 27 Council meeting. All three options included a fence and gate, and the design notes listed a preference for limiting access to Shavano Park residents.
The money comes from Loop 1604 sign lease revenues held in the city's Community Enhancement and Engagement Fund, approved in the FY2027 Budget. The city released a request for proposals in late September and received 13 bids. Council awarded the contract to Abelar on October 26, 2026. Work started 11 days later.
Living with the construction on Cliffside
By publish day, crews are in the excavation and rock milling week. The city's November 5 update lists the practical details:
- Expect traffic disruptions near the Cliffside bend.
- Cliffside Road is not planned to close at any point during construction.
- The city recommends against walking the existing rough-hewn path until the work is finished.
- Fence construction is planned for early December, as the concrete is completed.
For project updates, the city suggests texting COSP EVENTS to 91896. On the city calendar during the same stretch is the Winter Holiday Event on Saturday, December 5, from 3 to 6 p.m. at City Hall, 900 Saddletree Court. That puts the festival in the last week or so of trail work. The holiday event page has sign-up links for sponsoring and decorating a tree, and vendor spaces are limited.
Where the bottom of the trail leads
The new path leads down to the Salado Creek Greenway, part of the Howard W. Peak Greenway Trail System. The Phil Hardberger Park Conservancy describes that system as about 65 miles of multi-use, accessible trails and says the Salado Creek Greenway alone runs 20 miles. The City of San Antonio calls the northern section the Salado Creek Greenway North, from Loop 1604 to Rittiman Road, and describes it as a multi-use asphalt and concrete trail.
Some landmarks along the way, using the mileage each organization publishes:
- Toward Loop 1604. The Conservancy describes an 8-mile segment between Phil Hardberger Park and 1604, running between the bluffs along Salado Creek. The City's Salado Creek page lists the Loop 1604 Trailhead at 3104 N. Loop 1604 W.
- Through Phil Hardberger Park. Friends of San Antonio Natural Areas puts the stretch from Huebner Road through the park along Voelcker Lane to Walker Ranch Historical Landmark Park at 4.1 miles. The Greenway connects to the park's own trail network there. The City lists restrooms and a water fountain among the park's amenities.
- Over the Robert L.B. Tobin Land Bridge. The City's park map lists the bridge at 0.29 miles. The Conservancy's land bridge guide asks cyclists to walk their bikes across.
- East toward Rittiman Road. The Conservancy describes 12 miles from Blanco Road to Rittiman Road, lined with large pecan and live oak trees. Near Nacogdoches Road and Lady Bird Johnson Park, the trail crosses the 3,400-foot Morningstar Boardwalk over the Salado Creek wetland. It is named for Army Staff Sergeant Christopher Morningstar, a San Antonio native, and marked with an inlay of red, white and blue tile topped by a star.
While Voelcker is closed, the City lists the Phil Hardberger Park East Trailhead at 13203 Blanco Road as another way onto this part of the Greenway. The Conservancy calls that spot the Salado Outdoor Classroom. The City also has a standing note for every greenway: use caution before and after rain, never cross a trail that is under water, and expect mud and debris after storms.
Until the work wraps up
Until the concrete is done, the city recommends staying off the rough path at Cliffside, and the project page carries the latest schedule along with the plans for the fence and gate. The City's closures page is the place to check for temporary Greenway closures tied to the SAWS work through summer 2027.
I'm always glad to talk about Shavano Park, including small changes like a new path down to the creek that can shape your daily routine as much as the house does. If you have questions about the neighborhood or are thinking about your next move, Jen Romance would love to hear from you. Let's Connect.